Updates
-
4/27/15-Completed Main Spain Pier Design
-
4/21/15-Completed Footing Design/Immediate Settlement Analysis and Completed Ramp Pier Design
-
4/12/15-Completed Wing Wall Design
-
4/10/15-Completed Abutment Design
-
3/29/15-Completed Ramp Span Load Analysis
-
3/26/15-Preliminary Footing Design
-
3/18/15-Completed Final Main Span Girder Design
-
2/28/15-Settlement Analysis
-
2/20/15-Girder Selection Finalized
-
1/2/15 -Site Drive By for Inspection during Winter
-
11/13/14-Selection of Preliminary Girder
-
11/11/14-Preliminary Bearing Capacity Calcuated
-
10/28/14-Complete Deck Design using AASHTO Empirical Formulas
-
10/27/14-Soil Analysis Complete
-
10/21/14-Loading for Deck Design Complete
-
10/17/14-Completion of Soil Profile
-
9/19/14-In process of Load Analysis and the creation of Soil Profile
-
9/17/14-Meeting with NJDOT to discuss bridge design and program usage. Met with Jayant Dalal
-
9/12/14-Purchased AASHTO Pedestrian Bridge Specifications
-
9/10/14-Met with Dr. Al-Omaishi to discuss span design and AASHTO Pedestrian Bridge Specifications
-
9/9/14- Met with Dr. Kristic on borings and boring location plan
-
9/3/14- Presented proposal to Civil Engineering Department
-
8/29/14 - Site Visit to Sea Bright, NJ