Updates

 

  • 4/27/15-Completed Main Spain Pier Design

 

  • 4/21/15-Completed Footing Design/Immediate Settlement Analysis and Completed Ramp Pier Design

 

  • 4/12/15-Completed Wing Wall Design

 

  • 4/10/15-Completed Abutment Design

 

  • 3/29/15-Completed Ramp Span Load Analysis

 

  • 3/26/15-Preliminary Footing Design

 

  • 3/18/15-Completed Final Main Span Girder Design

 

  • 2/28/15-Settlement Analysis 

 

  • 2/20/15-Girder Selection Finalized

 

  • 1/2/15 -Site Drive By for Inspection during Winter

 

  • 11/13/14-Selection of Preliminary Girder

     

  • 11/11/14-Preliminary Bearing Capacity Calcuated

  •  

  • 10/28/14-Complete Deck Design using AASHTO Empirical Formulas

     

  • 10/27/14-Soil Analysis Complete

 

  • 10/21/14-Loading for Deck Design Complete

 

  • 10/17/14-Completion of Soil Profile

 

  • 9/19/14-In process of Load Analysis and the creation of Soil Profile

 

  • 9/17/14-Meeting with NJDOT to discuss bridge design and program usage. Met with Jayant Dalal

 

  • 9/12/14-Purchased AASHTO Pedestrian Bridge Specifications

 

  • 9/10/14-Met with Dr. Al-Omaishi to discuss span design and AASHTO Pedestrian Bridge Specifications

 

  • 9/9/14- Met with Dr. Kristic on borings and boring location plan 

 

  • 9/3/14- Presented proposal to Civil Engineering Department 

 

  • 8/29/14 - Site Visit to Sea Bright, NJ

 